Production ends before your stock arrives.
A factory quote often stops when goods are packed at the factory. Pickup, shipping, customs and receiving still lie ahead. Ask the supplier when their clock starts and stops.
This free calculator adds up the full lead time of a China order, from the day production starts to the day stock is ready to sell. Enter your days for five stages: production, domestic transport, international transport, customs and warehouse receiving. Then send the total to the safety stock calculator in one click.
Calculate Lead TimeA factory quote often stops when goods are packed at the factory. Pickup, shipping, customs and receiving still lie ahead. Ask the supplier when their clock starts and stops.
The date may depend on your deposit, sample approval or packing files. Holidays and rework can move it. Write these conditions down next to the date.
A shipping quote may stop at the port. Customs, trucking and receiving come after. Compare the start and end points before you add any times.
Lead time is the time between a set start event and a set finish event. In this calculator, it runs from the agreed start of your order to the day the stock is ready to sell, split into production, domestic transport, international transport, customs and warehouse receiving. Each stage needs its own source and the same kind of days, with no overlaps. A factory’s quote often covers only the first stage.
Cycle time is how long one round of a process takes, such as sewing one batch. Lead time is how long you wait from order to stock. They are not two names for the same number.
cycle time vs lead timeTotal lead time is the sum of five back-to-back stages, all counted in the same kind of days, from the agreed order trigger to stock ready to sell. Put waiting, inspection or handling inside the stage where it happens. If two stages overlap, map the real timeline instead of adding both in full. Enter zero for a stage that adds no time; leave an unknown stage blank.
Total days = production + domestic transport + international transport + customs + warehouse receiving
Enter a number of days for every stage; decimals are fine and a blank box stops the total. The sample buttons only show how the addition works, not standard times. Copy the record, then send the total to the safety stock calculator, where it fills in your average lead time only.
Supplier lead time is how long your next order takes to reach your warehouse; customer lead time is how long your buyer waits after ordering from you. With stock on the shelf, your customer may wait two days while your next inbound order takes two months. This calculator covers the inbound side, so its total is not a delivery promise.
| Type | Start | End | Who controls it |
|---|---|---|---|
| Supplier / inbound | Your order or deposit | Stock ready to sell | Supplier, forwarder and your warehouse |
| Customer / outbound | Customer places an order | Customer receives it | Your stock, packing and delivery carrier |
A factory’s standard lead time only means something once you know when it starts and ends. Ask whether rework is covered or only an order that goes right the first time, and keep the answers with your production number. Use the factory’s own holiday schedule rather than a general buffer.
| Check | What to write down |
|---|---|
| Start event | Deposit, sample approval or another trigger |
| Calendar | Calendar days or working days |
| Packing | Are cartons and packing inside the quote? |
| Inspection | Is final inspection inside the quote? |
| Changes | What changes would reset the date? |
A “7-day,” “2-week” or “30-day” lead time needs a start, a finish and a calendar before you can use it. Two calendar weeks are 14 days; two working weeks depend on the factory’s work days and holidays, and the calculator does not convert them. Ask what the phrase covers, note the quote date and enter the days in the right stage.
| Phrase | Questions to ask |
|---|---|
| 7 days | Starting when, counting which days, ending where? |
| 2 weeks | Calendar or working weeks? Which holidays? |
| 30 days | Does it include samples, production and inspection? |
| Delivery time | Which start and end points? What is left out? |
Use this lead time total as your average only if it fits how you plan; one order is not an average. The safety stock calculator also needs your average daily sales and a buffer, and for the peak method your highest daily sales and longest lead time. The one-click button carries only this total, so keep your longest lead time as its own number.
safety stock and reorder point calculatorShipping time goes in the international stage of your lead time. Check where the forwarder’s quote starts and ends, which mode it uses, and whether it already includes port waiting, so you do not add it twice. Transit times are typical ranges that change by route and season, so confirm them with your forwarder rather than plugging in a standard number.
shipping from China to the USA
We plan lead times by tracking planned and actual dates at each handoff, not just the final delay. At ASG we check these handoffs at our warehouses in Shenzhen and Dongguan. For the factory-to-warehouse leg, note four dates: factory ready, pickup, arrival and ready to ship. Write down each delay’s reason and who confirmed it, and use several past orders to see the normal spread.
Goods approved and packed. Note any changes or rework.
Pickup, arrival and paperwork ready.
Shipping scope, release and key dates.
Keep customs and receiving as two dates.
The lead time calculator works on one order at a time in your browser and does not save your inputs. Copy the result and store it with your sources, start and end points, and the date you checked it. When an input changes, run the numbers again rather than editing the total by hand. To compare plan with actual across orders, keep one row per order in a sheet.
see what the founding course coversAgree on the start event and the ready-to-sell finish. Pick calendar or working days before you collect any numbers.
Get each number from your supplier, forwarder or past orders. Leave unknown stages blank. Avoid overlaps.
Check every stage and every zero. Copy the record with its sources, so you can trace later changes.
Send the total to the safety stock calculator. Add your longest lead time and check your sales and buffer.
Lead time is the time from a set start event to a set finish event. In this calculator, it runs from your order start to the day stock is ready to sell, split into five stages. Agree on the start, the finish and the calendar before you compare quotes. A factory quote often covers production only.
The two types are supplier lead time and customer lead time. Supplier lead time is how long your next order takes to reach your warehouse. Customer lead time is how long your buyer waits after ordering from you. Stock on the shelf can make them very different. This calculator covers the supplier side.
A 2-week lead time usually means 14 calendar days, but you need to confirm it. Two working weeks depend on the factory’s work days and holidays. Ask when the clock starts and what event ends it. Then enter the days in the right stage. It rarely covers your whole import order.
Lead time covers the whole wait, from order start to stock you can sell. Delivery time often covers only the shipping leg. The words alone do not tell you the start and end points, so ask. In this calculator, delivery time is one part of the total. Count each stage once.
Common terms for lead time are replenishment time, order-to-receipt time and turnaround time. Each one can cover a different stretch, so check before you compare. Look at the start, the finish, the kind of days and the work included. This calculator uses one clear span: order start to stock ready to sell.
In Excel, give each of the five stages its own column, with the days, source and start and end points. Add them with =SUM() in a total column. Mark unknown stages clearly, because Excel treats blank cells as zero. Add a version date and plan-versus-actual columns. Use one calendar for every stage.
Keep your lead time total and stage notes with your next reorder plan, then use the safety stock calculator to turn it into a reorder point.